ARM Ferrous
Iron Ore division
Prices
Average realised US dollar export iron ore prices
were 79% higher on a free-on-board (FOB)
equivalent basis at US$156 per tonne (F2020:
US$87 per tonne) driven by robust steel production
in China and weather-related supply challenges in
key iron ore-producing countries like Brazil and
Australia. The 62% fines index (CIF China) reached
a high of US$233.75 per tonne in May 2021.
Average realised prices at our iron ore operations
were further enhanced by a strong rally in iron ore
lump premiums which also reached record levels.
The iron ore operations opportunistically increased
the ratio of lump to fines sales volumes from 54:46
in F2020 to 58:42 in F2021. A sustainable lump to
fines ratio for the operations is expected to be 55:45.
Volumes
Total iron ore sales volumes increased by 5% to
16.4 million tonnes (F2020: 15.6 million tonnes).
Export sales volumes were 1% higher at 13.3 million
tonnes (F2020: 13.1 million tonnes). Local sales
volumes were 29% higher at 3.1 million tonnes
(F2020: 2.4 million tonnes) due to above-plan
offtake from Arcelor Mittal South Africa.
Total iron ore production volumes decreased by
1% to 15.9 million tonnes (F2020: 16.1 million
tonnes) as higher production volumes at
Beeshoek Mine were offset by lower production
volumes at Khumani Mine due to compromised
water-supply reliability.
Production volumes at Khumani Mine were
impacted by challenges related to water supply
as the project to upgrade the Vaal Gamagara
Water Supply System was delayed. Assmang is
in extensive engagement with the Sedibeng Water
Board, the Department of Water Affairs and the
Minerals Council of South Africa to collaboratively
ensure that Phase 1 of the refurbishment
programme is completed, and that Phase 2 is
started in order to sustain water supply to the
area.
In total, 13.3 million tonnes of iron ore was railed
and exported through the Sishen-Saldanha export
channel, representing a deficit of just over one
million tonnes compared to planned volumes.
This was largely due to major operational and
maintenance challenges, major port equipment
breakdowns and abnormal weather conditions.
Engagements with Transnet are ongoing to
address these challenges.
Unit costs
On-mine unit production costs at Khumani Mine
increased to R289 per tonne (F2020: R251 per
tonne) mainly due to inflation, higher working cost
waste tonnages, the impact of Covid-19-related
expenses and lower production volumes.
On-mine unit production costs at Beeshoek
Mine increased to R263 per tonne
(F2020: R246) mainly due to inflation and
higher working cost waste tonnages, partially
offset by higher production volumes.
Unit cost of sales, which includes marketing and
distribution costs, were 16% higher mainly due
to the increase in unit production costs and sales
and marketing costs (driven by higher US dollar
iron ore prices) and an increase in sea-freight
rates per tonne.
Capital expenditure
Capital expenditure (100% basis) was
R2 397 million (F2020: R2 223 million), which
includes capitalised waste-stripping costs of
R851 million (F2020: R787 million).
Khumani Mine's capital expenditure (100%
basis) was 18% higher at R1 820 million
(F2020: R1 535 million) mainly due to increased
replacement fleet and an investment in an
automated discard spreader system aimed
at increasing production efficiencies. The
mine's capital expenditure includes capitalised
waste-stripping costs of R438 million
(F2020: R426 million).
Beeshoek Mine's capital expenditure (100%
basis) was R614 million (F2020: R670 million)
which includes capitalised waste-stripping costs
of R412 million (F2020: R361 million).
IRON ORE OPERATIONAL STATISTICS (100% BASIS)
|
unit |
F2021 |
F2020 |
% change |
Prices |
|
|
|
|
Average realised export price* |
US$/t |
156 |
87 |
79 |
Volumes |
|
|
|
|
Export sales |
000t |
13 269 |
13 129 |
1 |
Local sales |
000t |
3 148 |
2 439 |
29 |
Total sales |
000t |
16 417 |
15 568 |
5 |
Production |
000t |
15 928 |
16 092 |
(1) |
Export sales lump/fines split |
% |
58:42 |
54:46 |
|
Export sales CIF/FOB** split |
% |
55:45 |
48:52 |
|
Unit costs |
|
|
|
|
Change in on-mine production
unit costs |
% |
13 |
10 |
|
Change in unit cost of sales |
% |
16 |
10 |
|
Capital expenditure |
R million |
2 397 |
2 223 |
8 |
* Average realised export iron ore prices on an FOB equivalent basis.
** CIF – cost, insurance and freight; FOB - free-on-board.
Manganese ore operations
Prices
The index price for 44% manganese ore was
US$4.57/mtu (CIF Tianjin) at 30 June 2020,
declining to a low of US$4.09/mtu in July 2020.
At 30 June 2021, the index price recovered to
US$5.15/mtu.
The index price for carbonate manganese ore (37%
manganese ore CIF Tianjin) was US$4.21/mtu at
30 June 2020, dropping to a low of US$3.78/mtu
in July 2020. At 30 June 2021, the index price
recovered to US$4.71/mtu.
Manganese ore prices have remained lower than
expected during F2021 largely due to persistently
high inventory levels (particularly in China) and
increased global manganese ore supply.
Volumes
Manganese ore sales volumes increased by
22% from 3.2 million tonnes in F2020 to 3.9 million
tonnes in F2021 mainly as a result of easing
Covid-19 restrictions (compared to F2020) and
ramp up of the Black Rock and Gloria projects.
Export sales volumes were 22% higher at 3.8
million tonnes (F2020: 3.1 million tonnes) while
local sales volumes increased by 45% to 0.14
million tonnes (F2020: 0.10 million tonnes).
In total, 3.8 million tonnes of manganese ore was
railed and exported through the Port Elizabeth
Bulk Ore Terminal and Saldanha Multi-Purpose
Terminal. To mitigate rail losses due to Covid-19
in the earlier months of the year and to build up
port stocks, road transport was contracted for
approximately 185 000 tonnes from May 2020
to July 2020.
Transnet experienced challenges at the rail and
port due to operational issues. Engagements with
Transnet are ongoing to address these issues.
Further engagements with Transnet on rail and
port allocation beyond the current contractual
tonnages of 4.0 million tonnes per annum and
current contractual period until March/June 2023
are also progressing.
Production volumes at Black Rock Mine rose by
12% to 4.0 million tonnes as the Black Rock and
Gloria projects progressed. Production volumes
were negatively impacted by Covid-19-related
challenges, increasing community unrest and water supply challenges as discussed under iron
ore volumes (above) in the financial year
under review.
Unit costs
Black Rock Mine's on-mine unit production costs
were 18% higher at R699 per tonne (F2020:
R593 per tonne) mainly due to increased labour
costs, inefficiencies after delayed delivery of the
Black Rock and Gloria projects, Covid-19
compliance costs and above-inflation increases in
insurance and steel-based products. Labour cost
increases were driven by higher head count for
additional shifts worked, increased long-term
incentive expenses for A to C bands and higher
costs associated with Covid-19 absenteeism,
which resulted in 8 184 person-days lost in F2021
(including employees and contractors). Unit
production cost improvements expected from the
Black Rock and Gloria projects were not realised
due to delays in commissioning certain Black
Rock project and Gloria project systems. Unit
production costs are expected to improve as
completion and ramp up of the two projects
delivers improved efficiencies.
Unit cost of sales (which include marketing and
distribution costs) increased by 8% as a result of
higher sales and marketing costs due to higher
revenue, increased freight rates, higher on-mine
unit production costs and increased depreciation
as the Black Rock and Gloria projects move to
commissioning phase.
Capital expenditure
Total capital expenditure for the manganese ore
operations was R2 060 million on a 100% basis
(F2020: R2 260 million) of which R845 million
(F2020: R846 million) related to the Gloria project.
At 30 June 2021, 84% of the approved capital of
R3 billion was spent on the Gloria project and
95% of the approved capital of R7.2 billion was
spent on the Black Rock project.
The Black Rock and Gloria projects aim to
modernise and expand the mine's output by
increasing volumes and flexibility to produce
various grades of manganese ore at the three
operating shafts while improving efficiencies.
Ramp up of the Black Rock Mine operations is
being closely synchronised with Transnet's rail
availability and is informed by prevailing market
conditions.
The estimated date of completion of the Black
Rock and Gloria projects is August 2022. Difficult
ground conditions in mining areas, complex
geology, various labour incidents and Covid-19
resulted in delays on the estimated completion
date. The Nchwaning 3 silo feed and satellite
tip 1 systems were successfully commissioned
and handed over to operations at the end of
June 2021. The Nchwaning II Graben system is
due for commissioning by September 2021.
MANGANESE ORE OPERATIONAL STATISTICS (100% BASIS)
|
unit |
F2021 |
F2020 |
% change |
Volumes |
|
|
|
|
Export sales |
000t |
3 823 |
3 128 |
22 |
Domestic sales* |
000t |
143 |
99 |
45 |
Total sales |
000t |
3 966 |
3 227 |
23 |
Production |
000t |
4 041 |
3 619 |
12 |
Unit costs |
|
|
|
|
Change in on-mine production unit costs |
% |
18 |
(2) |
|
Change in unit cost of sales |
% |
8 |
– |
|
Capital expenditure |
R million |
2 060 |
2 228 |
(8) |
* Excluding intra-group sales of 187 247 tonnes sold to Cato Ridge Works (F2020: 208 572 tonnes).
MANGANESE ORE FINANCIAL INFORMATION
R million |
F2021 |
F2020 |
% change |
Sales |
10 236 |
9 005 |
14 |
Operating profit |
1 202 |
2 595 |
(54) |
Contribution to headline earnings |
823 |
1 846 |
(55) |
Capital expenditure |
2 060 |
2 260 |
(9) |
Depreciation |
716 |
588 |
22 |
EBITDA |
1 918 |
3 183 |
(40) |
Manganese alloys operations
Prices
Average realised prices for high-carbon manganese
alloy and medium-carbon manganese alloy at
Cato Ridge Works decreased by 12% to US$937
per tonne (F2020: US$1 065 per tonne) and by
11% to US$1 364 per tonne (F2020: US$1 533 per
tonne), respectively.
Volumes
High-carbon manganese alloy production at
Sakura Ferroalloys (100% basis) decreased to
191 000 tonnes (F2020: 232 000 tonnes) mainly
due to multiple transformer failures in January, April
and May 2021. The April transformer failure left
Furnace 1 out of operation as the only spare
transformer was used during the first transformer
failure that occurred in January 2021.
Sakura Ferroalloys declared force majeure on its
customers due to lower-than-planned production
caused by these events. Based on current planning,
Furnace 1 is expected to be switched on by the
end of September 2021.
High-carbon manganese alloy sales volumes
(100% basis) increased by 1% to 218 000 tonnes
(F2020: 216 000 tonnes). The impact of the
transformer failures on high-carbon manganese alloy
sales volumes for F2021 was limited as sufficient
stock levels were available to service contracts.
High-carbon manganese alloy production at Cato
Ridge Works decreased by 3% to 123 500 tonnes
(F2020: 127 100 tonnes). Medium-carbon
manganese alloy production at Cato Ridge Alloys
(100% basis) decreased by 4% to 48 000 tonnes
(F2020: 49 500 tonnes).
High-carbon manganese alloy sales at Cato Ridge
Works increased by 17% to 76 000 tonnes
(100% basis) (F2020: 65 000 tonnes). Medium-carbon
manganese alloy sales at Cato Ridge Alloys
(100% basis) increased by 37% to 58 100 tonnes
(F2020: 42 400 tonnes).
Unit costs
Unit production costs at Sakura Ferroalloys
increased by 1% from MYR3 691 per tonne
in F2020 to MYR3 736 per tonne in F2021.
Unit production costs at Cato Ridge Works
increased by 11% from R11 504 per tonne in
F2020 to R12 798 per tonne in F2021 mainly due
to lower production volumes, above-inflation power
escalations and the variability of the ore grade.
Medium-carbon manganese alloy unit production
costs at Cato Ridge Alloys decreased by 0.4% from
R18 302 per tonne in F2020 to R18 221 per tonne
in F2021 due to a reduction in the cost for molten
metal.
MANGANESE ALLOY OPERATIONAL STATISTICS (100% BASIS)
|
unit |
F2021 |
F2020 |
% change |
Volumes |
|
|
|
|
Cato Ridge Works sales* |
000t |
76 |
65 |
17 |
Cato Ridge Alloys sales |
000t |
58 |
42 |
37 |
Sakura sales |
000t |
218 |
216 |
1 |
Cato Ridge Works production |
000t |
124 |
127 |
(3) |
Cato Ridge Alloys production |
000t |
48 |
50 |
(4) |
Sakura production |
000t |
191 |
232 |
(18) |
Unit costs – Cato Ridge Works |
|
|
|
|
Change in on-mine unit production costs |
% |
11 |
13 |
|
Change in unit cost of sales |
% |
5 |
– |
|
Unit costs – Cato Ridge Alloys |
|
|
|
|
Change in on-mine production unit costs |
% |
(1) |
(2) |
|
Change in unit cost of sales |
% |
– |
1 |
|
Unit costs – Sakura |
|
|
|
|
Change in on-mine production unit costs |
% |
1 |
(23) |
|
Change in unit cost of sales |
% |
1 |
(17) |
|
* Excluding intra-group sales of 57 431 tonnes sold to Cato Ridge Alloys (F2020: 59 841 tonnes).
MANGANESE ALLOY FINANCIAL INFORMATION
R million |
F2021 |
F2021 |
% change |
Sales |
1 956 |
2 293 |
(15) |
Operating profit |
162 |
255 |
(37) |
Contribution to headline earnings |
74 |
(228) |
|
Capital expenditure |
188 |
54 |
248 |
Depreciation |
58 |
70 |
(17) |
EBITDA |
220 |
356 |
(38) |
The ARM Ferrous operations, held through its 50% investment in Assmang Proprietary Limited
(Assmang), comprise the iron ore and manganese divisions. Assore Limited, ARM's partner in
Assmang, owns the remaining 50%.
ARM Platinum
Prices
Higher metal prices, particularly rhodium which
increased by 179% in F2021, contributed
significantly to the Modikwa and Two Rivers
mines' F2021 results. Despite a slightly stronger
rand/US dollar exchange rate, the average rand
per 6E kilogram basket price increased by
71% and 74% to R1 457 843/kg (F2020:
R850 909/kg) and R1 349 148/kg (F2020:
R775 857/kg) for Modikwa and Two Rivers
mines, respectively.
US dollar nickel prices were 18% higher, which
contributed to Nkomati Mine's cash position.
AVERAGE US DOLLAR METAL PRICES
|
unit |
F2021 |
F2020 |
% change |
Platinum |
US$/oz |
1 046 |
871 |
20 |
Palladium |
US$/oz |
2 427 |
1 901 |
28 |
Rhodium |
US$/oz |
17 478 |
6 275 |
179 |
Nickel |
US$/t |
16 447 |
13 964 |
18 |
Copper |
US$/t |
8 086 |
5 647 |
43 |
Cobalt |
US$/lb |
18 |
16 |
12 |
UG2 chrome concentrate – Two Rivers (CIF*) |
US$/t |
137 |
134 |
2 |
High sulphur chrome concentrate – Nkomati (FOT*) |
US$/t |
43 |
48 |
(10) |
* CIF – cost, insurance and freight; FOT – free-on-truck.
AVERAGE RAND METAL PRICES
|
unit |
F2021 |
F2020 |
% change |
Average exchange rate |
R/US$ |
15.39 |
15.68 |
(2) |
Platinum |
R/oz |
16 107 |
13 658 |
18 |
Palladium |
R/oz |
37 360 |
29 812 |
25 |
Rhodium |
R/oz |
269 071 |
98 399 |
173 |
Nickel |
R/t |
253 194 |
218 948 |
16 |
Copper |
R/t |
124 482 |
88 549 |
41 |
Cobalt |
R/lb |
283 |
257 |
10 |
UG2 chrome concentrate – Two Rivers (CIF*) |
R/t |
2 107 |
2 100 |
– |
High sulphur chrome concentrate – Nkomati (FOT*) |
R/t |
662 |
748 |
(12) |
* CIF – cost, insurance and freight; FOT – free-on-truck.
Two Rivers Mine
Volumes
PGM volumes increased from 261 024 6E
ounces in F2020 to 300 172 6E ounces in F2021.
Production rates are returning to normal after
the Covid-19-related national lockdown and
operational challenges in F2020.
The sinking of declines at Main shaft is
progressing as planned with completion beyond
level 13. This is improving mining flexibility to
optimise the blend from normal and split reefs.
Mining of the split-reef is being managed with
various cuts to optimise the grade.
PGM grades from North shaft have improved
with this ore given processing priority at the
concentrator plant.
Chrome concentrate sales volumes increased
by 41% to 242 945 tonnes (F2020: 172 368).
This, combined with a stable rand chrome price,
resulted in chrome cash operating profit
improving by 18% to R118 million (F2020:
R100 million).
Unit costs
Unit production costs on a rand per tonne
milled basis increased in line with inflation by
5% to R905 per tonne (F2020: R857 per tonne).
The rand per 6E PGM ounce cost reduced to
R9 893 per 6E PGM ounce (F2020: R9 908 per
6E PGM ounce), as a direct result of improved
plant recoveries and cost containment.
Capital expenditure
Of the R1 281 million capital spent at Two
Rivers Mine (F2020: R813 million), R210 million
was for fleet replacement and refurbishment.
Deepening the Main and North declines with
respective electrical and mechanical installations
accounted for R285 million of total capital
expenditure. Capital expenditure on the new
tailings dam and plant expansion was
R294 million and R290 million, respectively.
Covid-19 restrictions and steel shortages delayed
the plant expansion project completion date by
two months. The additional mill is now expected
to be commissioned in November 2021 with full
ramp-up expected to be achieved in the third
quarter of F2022.
Construction of the new tailings dam project was
also delayed by Covid-19 and is expected to be
finalised in October 2021.
Two Rivers' shareholders approved the Merensky
Project which involves mining the Merensky
Reef. Total capital expenditure for the project is
R5.7 billion (100% basis) which will be spent
over three years. The project entails annual
production of 182 000 6E PGM ounces,
1 600 tonnes nickel, and 1 300 tonnes of copper.
Merensky underground mining is planned to
commence in the fourth quarter of F2022, with
the plant set to be commissioned in the second
quarter of F2024.
TWO RIVERS MINE OPERATIONAL STATISTICS (100% BASIS)
|
unit |
F2021 |
F2020 |
% change |
Cash operating profit |
R million |
8 949 |
3 535 |
153 |
– PGMs |
R million |
8 832 |
3 435 |
157 |
– Chrome |
R million |
118 |
100 |
18 |
Tonnes milled |
Mt |
3.28 |
3.02 |
9 |
Head grade |
g/t 6E |
3.43 |
3.45 |
(1) |
PGMs in concentrate |
ounces 6E |
300 172 |
261 024 |
15 |
Chrome in concentrate sold |
tonnes |
242 945 |
172 368 |
41 |
Average basket price |
R/kg 6E |
1 349 148 |
775 857 |
74 |
Average basket price |
US$/oz 6E |
2 724 |
1 540 |
77 |
Cash operating margin |
% |
73 |
55 |
|
Cash cost |
R/kg 6E |
318 075 |
318 534 |
– |
Cash cost |
R/tonne |
905 |
857 |
5 |
Cash cost |
R/Pt oz |
21 341 |
21 127 |
1 |
Cash cost |
R/oz 6E |
9 893 |
9 908 |
– |
Cash cost |
US$/oz 6E |
643 |
632 |
2 |
Modikwa Mine
Volumes
Tonnes milled increased by 5% which was more
than offset by a 7% decrease in head grade,
reducing PGM production by 3% to 251 755 6E
PGM ounces (F2020: 259 360 6E PGM ounces).
The decline in head grade was mainly due to
increased production from on-reef development
at North shaft. Mining volumes were impacted
by safety stoppages and industrial action by
employees in the first half of the year. Measures
implemented to prevent the spread of Covid-19
impacted the operation throughout the financial
year due to high labour intensity.
The accelerated on-reef development is
progressing to open stoping panels.
Mining volumes were impacted by Covid-19
restrictions with a proportionally larger impact
on stoping than on development, given the higher
labour intensity of stoping. The resultant lower
stoping:development ratio gave rise to a decrease
in head grade. More ore milled from historical
low-grade stockpiles also contributed to reduced
head grades.
In addition, in the first half of the financial year,
Modikwa Mine lost approximately 5 200 6E PGM
ounces following two fatal accidents. An
additional estimated 14 800 6E PGM ounces were
lost towards the end of 1H F2021 due to
unprotected industrial action by National Union of
Mineworkers (NUM) affiliated employees. This
related to housing-related benefits which were
overpaid in the fourth quarter of F2020 and
employees incorrectly claiming that the mine
owed them monies under the Temporary
Employer/Employee Relief Scheme (TERS). All
employees returned to work and the matter was
resolved.
Production volumes at the mine improved in
the second half of the financial year with the
resolution of the above issues.
Unit costs
Unit production costs increased by 19%
on both 6E PGM ounce and rand per tonne
basis to R14 300 per 6E PGM ounce
(F2020: R11 974 per 6E PGM ounce) and
R1 757 per tonne (F2020: R1 598 per tonne).
This was due to lower production volumes
and Covid-19-related costs.
Capital expenditure
Capital expenditure at Modikwa Mine (100%
basis) increased by 3% to R660 million
(F2020: R638 million). Of this, R238 million
related to construction of the chrome recovery
plant, R62 million to fleet refurbishment and
critical spares, R55 million for the North shaft
deepening project and R43 million for the South
shaft deepening project.
To maintain the current production profile and
ramp-up production, Modikwa Mine initiated the
North shaft and South 2 shaft projects:
- North shaft project – level 9 decline equipping was completed and commissioned. Level 9 strike development has started. The decline to level 10 is scheduled to commence in the first quarter of F2022
- South 2 shaft system produced an average of 51 258 tonnes per month in F2021. The project is on track and the opening of more working areas in the system achieved an average of 57 795 tonnes per month in 2H F2021. The mine is ramping up production.
Commissioning of the Chrome Recovery Plant (CRP) is underway as planned. Ramp up to nameplate capacity rate is envisaged in the second half of F2022.
MODIKWA MINE OPERATIONAL STATISTICS (100% BASIS)
|
unit |
F2021 |
F2020 |
% change |
Cash operating profit |
R million |
6 248 |
3 079 |
103 |
Tonnes milled |
Mt |
2.05 |
1.94 |
5 |
Head grade |
g/t 6E |
4.51 |
4.82 |
(7) |
PGMs in concentrate |
6E oz |
251 755 |
259 360 |
(3) |
Average basket price |
R/kg 6E |
1 457 843 |
850 909 |
71 |
Average basket price |
US$/oz 6E |
2 945 |
1 688 |
75 |
Cash operating margin |
% |
63 |
50 |
|
Cash cost |
R/kg 6E |
459 745 |
384 984 |
19 |
Cash cost |
R/tonne |
1 757 |
1 598 |
10 |
Cash cost |
R/Pt oz |
36 405 |
30 746 |
18 |
Cash cost |
R/oz 6E |
14 300 |
11 974 |
19 |
Cash cost |
US$/oz 6E |
929 |
764 |
22 |
Nkomati Mine
Nkomati Mine was placed on care and
maintenance in March 2021 in line with
the strategy as planned and previously
communicated.
Estimated rehabilitation costs
As at 30 June 2021, the estimated undiscounted
rehabilitation costs attributable to ARM were
determined to be R679 million (30 June 2020:
R620 million) excluding VAT (discounted
R596 million). The R59 million increase was
due to increased contractor rates and inflation.
At 30 June 2021, R109 million (attributable to
ARM) cash and financial assets were available to
fund rehabilitation obligations for Nkomati Mine.
The resulting attributable shortfall of R487 million
is expected to be funded by ARM.
Nkomati Mine's estimated rehabilitation costs
continue to be reassessed as engineering
designs evolve and new information becomes
available.
Volumes
Nkomati Mine ceased mining in February 2021.
Nickel production for the nine months amounted
to 8 016 tonnes (F2020: 10 638 tonnes). The last
ore was processed through the concentrator plant
in March 2021.
Chrome concentrate sales volumes were
116 298 tonnes (F2020: 222 110 tonnes) which,
combined with a 10% reduction in average
realised US dollar chrome prices, resulted in a
cash operating loss from chrome of R7 million
(F2020: R42 million cash operating profit).
Unit costs
On-mine unit production costs in F2021 were only
1% higher at R384 per tonne (F2020: R380 per
tonne).
Unit cash costs net of by-products per nickel
produced in F2021 were 53% lower at US$2.98/lb
(F2020: US$6.29/lb). The improvement in unit
cash costs was due to increased by-product
credits.
NKOMATI MINE OPERATIONAL STATISTICS (100% BASIS)
|
unit |
F2021 |
F2020 |
% change |
Cash operating profit |
R million |
750 |
14 |
>200 |
– Nickel |
R million |
758 |
(28) |
|
– Chrome |
R million |
(7) |
42 |
|
Cash operating margin |
% |
24 |
1 |
|
Tonnes milled |
Mt |
4.70 |
6.62 |
(29) |
Head grade |
% nickel |
0.25 |
0.25 |
– |
On-mine cash cost per tonne milled |
R/tonne |
384 |
380 |
1 |
Cash costs net of by-products* |
US$/lb |
2.98 |
6.29 |
(53) |
Contained metal |
|
|
|
|
Nickel |
tonnes |
8 016 |
10 638 |
(25) |
PGMs |
ounces |
67 144 |
80 684 |
(17) |
Copper |
tonnes |
4 409 |
5 169 |
(15) |
Cobalt |
tonnes |
500 |
616 |
(19) |
Chrome concentrate sold |
tonnes |
116 298 |
222 110 |
(48) |
* This reflects US dollar cash costs net of by-products (PGMs and chrome) per pound of nickel produced.
ARM Coal
Prices
Thermal coal prices increased in F2021 due
to the global economic recovery and supply
shortages.
Global coal prices were supported after China
increased demand for non-Australian thermal
coal. Increased safety inspections at coal mines
and enforcement of compliance to licensed
production capacity restricted coal supply out
of China. Prices were further assisted by the
delayed start to the China hydro-generation
season which increased thermal power
generation compared to the prior year.
The Asian Liquefied Natural Gas (LNG) price
increase to record levels resulted in LNG to
coal switching, which further supported additional
coal demand.
The impact of the higher market prices was
reduced by increased exports of low-grade
quality coal due to decreased domestic demand.
Goedgevonden Mine's average received US dollar
prices increased by 19% to US$57 per tonne in
F2021 (F2020: US$48 per tonne). PCB's average
received US dollar prices increased by 12% from
US$51 per tonne in F2020 to US$57 per tonne in
F2021.
Approximately 56% (F2020: 62%) of export
volumes at Goedgevonden Mine was high-quality
coal while PCB exports of high-quality coal
amounted to 62% (F2020: 65%).
Goedgevonden Mine
Volumes
Production was negatively impacted by
challenges at Transnet Freight Rail, giving rise to
full stockpiles at the mine. The underperformance
was exacerbated by a derailment on the coal line
in April 2021. Inclement weather in January and
February 2021 also affected run-of-mine
production.
The Covid-19 impact on production losses
reduced in 2H F2021 due to improved protocols
and management thereof.
ARM's attributable run-of-mine production from
Goedgevonden Mine reduced by 16% from
2.85 million tonnes in F2020 to 2.39 million tonnes
in F2021, while attributable saleable production
was 1.5 million tonnes in F2021 compared to
1.76 million tonnes in F2020.
Unit costs
On-mine unit production costs per saleable tonne
rose by 17% to R506 per tonne (F2020: R431 per
tonne). The above-inflation increase in unit costs
was due mainly to a 15% reduction in saleable
production volumes.
GOEDGEVONDEN MINE OPERATIONAL STATISTICS
|
unit |
F2021 |
F2020 |
% change |
Total production and sales (100% basis) |
|
|
|
|
Saleable production |
Mt |
5.79 |
6.77 |
(15) |
Export thermal coal sales |
Mt |
3.89 |
4.29 |
(9) |
Domestic thermal coal sales |
Mt |
1.90 |
2.25 |
(16) |
ARM attributable production and sales |
|
|
|
|
Saleable production |
Mt |
1.50 |
1.76 |
(15) |
Export thermal coal sales |
Mt |
1.01 |
1.12 |
(9) |
Domestic thermal coal sales |
Mt |
0.49 |
0.59 |
(16) |
Average received coal price |
|
|
|
|
Export (FOB*) |
US$/t |
56.73 |
47.87 |
19 |
Domestic (FOT**) |
R/t |
354 |
305 |
16 |
Unit costs |
|
|
|
|
On-mine saleable cost |
R/t |
506 |
431 |
17 |
Capital expenditure |
R million |
1 011 |
757 |
33 |
* FOB – free-on-board.
** FOT – free-on-truck.
GOEDGEVONDEN MINE (GGV) ATTRIBUTABLE HEADLINE EARNINGS/(LOSS) ANALYSIS
R million |
F2021 |
F2020 |
% change |
Cash operating profit |
148 |
56 |
164 |
Amortisation and depreciation |
(182) |
(197) |
7 |
Imputed interest and other* |
(170) |
(160) |
(6) |
Loan re-measurement gain |
206 |
207 |
– |
Impairment loss |
– |
(559) |
|
Profit/(loss) before tax |
2 |
(653) |
|
Add: Impairment loss |
– |
559 |
(100) |
Add: tax |
8 |
56 |
(86) |
Headline earnings/(loss) attributable to ARM |
10 |
(38) |
|
* Post restructuring the ARM Coal loans, all interest expense on partner loans is imputed.
Participative Coal Business (PCB)
Volumes
During the year, the PCB operations were
significantly impacted by challenges at Transnet
Freight Rail. This resulted in full product stockpiles
at both Impunzi and Tweefontein restricting
production.
In the second half of the financial year, production
at Tweefontein Mine was further impacted by hot
coal and hard digging conditions at the Klipplaat
pit. These conditions are expected to improve in
F2022 as most of the production will come from
the Makoupan pit. A programme of re-drilling and
blasting hot areas where practical to improve
digging conditions in Klipplaat has also been
implemented.
ARM's attributable run-of-mine production from
PCB reduced by 11%, from 4.28 million tonnes
in F2020 to 3.79 million tonnes in F2021.
Export sales volumes were 3% higher at 8 million
tonnes (F2020: 7.73 million tonnes). Domestic
sales volumes declined from 5.74 million tonnes
to 2.9 million tonnes largely due to decreased
sales to Eskom.
ARM's attributable saleable production reduced
by 13% from 2.69 million tonnes in F2020 to
2.34 million tonnes in F2021.
PCB successfully commissioned a second
dragline at Tweefontein Mine in the latter part
of 1H F2021. This is expected to improve both
production and cost management.
Unit costs
Unit production costs per saleable tonne
increased by 7% from R484 per tonne in F2020
to R520 per tonne in F2021, mainly due to lower
saleable production volumes.
PCB OPERATIONAL STATISTICS
|
Unit |
F2021 |
F2020 |
% change |
Total production sales (100% basis) |
|
|
|
|
Saleable production |
Mt |
11.58 |
13.34 |
(13) |
Export thermal coal sales |
Mt |
8.00 |
7.73 |
3 |
Domestic thermal coal sales |
Mt |
2.90 |
5.74 |
(49) |
ARM attributable production and sales |
|
|
|
|
Saleable production |
Mt |
2.34 |
2.69 |
(13) |
Export thermal coal sales |
Mt |
1.62 |
1.56 |
3 |
Domestic thermal coal sales |
Mt |
0.59 |
1.16 |
(49) |
Average received coal price |
|
|
|
|
Export (FOB)* |
US$/tonne |
56.97 |
50.54 |
13 |
Domestic (FOT)** |
R/tonne |
678 |
666 |
2 |
Unit costs |
|
|
|
|
On-mine saleable cost |
R/tonne |
520 |
484 |
7 |
Capital expenditure |
R million |
1 226 |
2 286 |
(46) |
* FOB – free-on-board.
** FOT – free-on-truck.
PCB ATTRIBUTABLE HEADLINE (LOSS)/EARNINGS ANALYSIS
R million |
F2021 |
F2020 |
% change |
Cash operating profit |
299 |
304 |
(2) |
Imputed interest |
(104) |
(118) |
(12) |
Amortisation and depreciation |
(569) |
(479) |
19 |
Loan re-measurement gain |
36 |
278 |
(87) |
Loss on sale of asset |
– |
(2) |
|
Impairment loss |
– |
(1 121) |
|
Loss before tax |
(338) |
(1 138) |
(70) |
Add: impairment |
– |
1 123 |
|
Add: tax |
78 |
51 |
53 |
Headline (loss)/earnings attributable to ARM |
(260) |
36 |
– |
ARM's economic interest in PCB is 20.2%. PCB consists of two large mining complexes in Mpumalanga.
ARM has a 26% effective interest in the Goedgevonden Mine near Ogies in Mpumalanga.
Harmony
ARM's investment in Harmony was negatively
revalued by R1 426 million in F2021 (F2020:
R2 996 million positive revaluation) as
the Harmony share price decreased by 27% from
R71.86 per share at 30 June 2020 to R52.76 per
share at 30 June 2021. The Harmony investment
is therefore reflected on the ARM statement of
financial position at R3 940 million based on its
share price at 30 June 2021.
Gains are accounted for, net of deferred
capital gains tax, through the statement of
comprehensive income. Dividends from Harmony
are recognised in the ARM statement of profit or
loss on the last day of registration following
dividend declaration.
Harmony declared a final dividend of 27 cents
per share, bringing their total dividend for F2021
to 137 cents per share.
Harmony's financial performance for F2021
reflects a net profit increase of 758% to
R5 590 million compared to a net loss of
R850 million in F2020. Headline earnings
improved to 923 cents per share compared with
a headline loss of 154 cents per share for F2020.
Revenue increased by R12 488 million or 43%
to R41 733 million, mainly due to the operational
expansion from the acquisition of Mponeng and
related assets as well as an increase in the gold
price received.
Production costs increased by R7 726 million
or 35% to R29 774 million during F2021
predominantly due to the operational expansion
as well as annual price increases.
As at 30 June 2021, net debt decreased by
R819 million to R542 million. The cash generated
by operations was sufficient to pay for capital
expenditure, a dividend and significantly reduce
the group's debt.
The reduction in debt as well as the stronger rand
resulted in lower finance costs incurred during
F2021 of R228 million compared with R424 million
in F2020.
Harmony's results for the year ended 30 June
2021 can be found on Harmony's website:
www.harmony.co.za