Thando Mkatshana
Chief executive – ARM Platinum
Decline in average realised US dollar PGM prices
162% decrease in headline earnings
Two Rivers Mine Merensky project placed on care and maintenance
Improved grade at Modikwa Mine supported increased production volumes
Conserving cash at Bokoni Mine while ramping up production in phased and measured manner
ARM Platinum headline earnings decreased by 162% to a headline loss of R910 million (F2023: R1.5 billion earnings), largely due to the sharp decline in PGM prices in F2024 and above-inflation increases in unit cash costs.
Volumes
Tonnes milled decreased 4%. However, the grade improved by 6% owing to increased off-reef development, resulting in a 1% improvement in production volumes to 289 751 6E PGM ounces (F2023: 285 910 6E PGM ounces).
Unit costs
Unit cash costs were up 6% to R18 837 per 6E PGM ounce (F2023: R17 728 per 6E PGM ounce) and 12% higher on a rand/tonne basis at R2 270 (F2023: R2 021) owing to the reduction in tonnes milled.
Volumes
Tonnes milled were 1% lower than F2023. The UG2 grade remains a constraint due to the split reef at 3.1g/t while Merensky grade was lower at 2.1g/t as the operation was developing to open more ground. PGM production volumes declined 1% to 291 408 6E PGM ounces (F2023: 295 441 6E PGM ounces). Following accelerated development of the declines, mining flexibility is expected to improve.
Unit costs
Two Rivers Mine unit cash costs increased 16% to R1 282 per tonne milled (F2023: R1 105 per tonne). The rand per 6E PGM ounce cash cost rose 17% to R15 589 per ounce (F2023: R13 376 per ounce), owing to milling Merensky ore, which is at a lower grade than UG2, resulting in lower ounces produced. Various cash preservation and cost-saving initiatives have been implemented at Two Rivers Mine, including rightsizing the labour complement.
Progress to date
The current priority is to conserve cash while ramping up production in a phased and measured manner given depressed commodity prices. This approach will maximise the use of Bokoni Mine’s existing surface and concentrator plant infrastructure, reducing capital costs. Subsequent to year end, the construction of a chrome recovery plant was approved by the board.
Nkomati Mine
Nkomati Mine has been on care and maintenance since F2021.
ARM and Norilsk Nickel Africa Proprietary Limited concluded a sale agreement that provides for ARM to acquire Norilsk Nickel Africa’s 50% participation interest in Nkomati Mine for cash of R1 million. The transaction is subject to certain conditions precedent, with the main outstanding condition precedent being official consent in terms of section 11 of the Mineral and Petroleum Resources Development Act 28 of 2002.
At 30 June 2024, the estimated undiscounted rehabilitation costs attributable to ARM were determined to be R1 191 million (30 June 2023: R932 million) excluding VAT. The increase in the undiscounted liability of R259 million is attributed mainly to the provision for the water treatment plant.
The discounted rehabilitation costs attributable to ARM were determined to be R1 119 million (30 June 2023: R802 million).
At 30 June 2024, R137 million (attributable to ARM) in cash and financial assets was available to fund rehabilitation obligations for Nkomati Mine. The resulting attributable shortfall in discounted rehabilitation costs of R982 million is expected to be funded by ARM.
Nkomati Mine’s estimated rehabilitation costs continue to be reassessed as engineering designs evolve and new information becomes available.