Operational review

Key features for F2026

GGV saleable production increased by 2% and PCB increased by 1%

a result of improved performance from TFR

Realised average export coal prices

decreased by 5% at GGV and 3% at PCB

Significant points

Unit cost increases at GGV and PCB in line with inflation

Domestic sales volumes declined by 17%

THANDO MKATSHANA

Chief executive – ARM Technical Services

Scorecard

Goedgevonden Mine (GGV)
Participative Coal Business (PCB)
Goedgevonden Mine (GGV)

Goedgevonden Mine (GGV)

F2026 OBJECTIVES
  • Continued focus on containing unit cost escalations below inflation.
ACHIEVED/NOT ACHIEVED
  • Achieved
    On-mine unit production costs increased by 5%.
F2027 OBJECTIVES
  • Continued focus on containing unit cost escalations below inflation.
Participative Coal Business (PCB)

Participative Coal Business (PCB)

F2026 OBJECTIVES
  • Continued focus on containing unit cost escalations below inflation.
ACHIEVED/NOT ACHIEVED
  • Achieved
    Unit production costs increased by 2%.
F2027 OBJECTIVES
  • Continued focus on containing unit cost escalations below inflation.

Thermal coal prices

GGV's average export coal price received decreased by 5% to US$78/tonne (F2025: US$82/tonne). PCB's average export coal price received decreased by 3% to US$73/tonne (F2025: US$75/tonne).

API4 commodity prices recovered marginally in 2H F2026 from depressed market conditions in 1H F2026. The global coal market experienced resilient demand in 2H F2026 amid geopolitical-related price increases, particularly Middle East tensions, and weather-related restocking. In addition, China's coal market experienced declining domestic production and weak wind output, resulting in thermal coal price support.

Approximately 71% and 65% of export volumes at GGV Mine and PCB, respectively, comprised high-quality coal. Export revenue in F2026 was negatively impacted by the average realised rand strengthening by 7% versus the US dollar.

Financial performance

ARM Coal reported a headline loss of R428 million (F2025: R47 million earnings), mainly driven by a decrease in the realised coal price as well as the average realised rand strengthening by 7% versus the US dollar.

The GGV recorded a headline loss of R73 million (F2025: R134 million earnings). PCB recorded a headline loss of R355 million (F2025: R87 million loss).

Operational performance

Goedgevonden Mine

ARM attributable saleable production increased by 2% to 1.78 million tonnes (F2025: 1.74 million tonnes). Transnet Freight Rail (TFR) performance improved marginally during the reporting period, enabling increased production.

On-mine unit production costs per saleable tonne increased by 5% to R668 per tonne (F2025: R634 per tonne), as the impact of higher diesel prices was partially offset by the increased saleable production.

Participative Coal Business

Export sales volumes at the PCB operation increased by 3% to 8.2 million tonnes (F2025: 8.0 million tonnes), mainly as a result of improved performance from TFR. Domestic sales volumes declined by 17% to 0.99 million tonnes (F2025: 1.19 million tonnes) largely due to decreased coal sales to Eskom.

ARM attributable saleable production increased by 2% to 1.92 million tonnes in F2026 (F2025: 1.89 million tonnes).

Unit production costs per saleable tonne increased by 2% to R867 per tonne (F2025: R849 per tonne).